Offline tool for ground support checks

I built a small offline sheet for quick stand-up time and bolt layout checks underground, keyed to RMR/Q and span, because we kept overrunning the 30-minute unsupported window in a 3.5 m heading. If it helps, I can share the PDF/Excel — includes a simple FoS estimate, suggested 2.4 m resin bolts at 1.5 m centers with 50 mm early-strength shotcrete for RMR 55–65, and a rainfall trigger that flags >25 mm in 24 h.

‌⁠‍⁠​‍​‍‌⁠‌​​‍​‍​⁠‍‍​‍​‍‌‍‌⁠‌‍⁠‌‌‍‍‍​⁠​‍​‍​‍​‍⁠​​‍​‍‌‍‍⁠​‍​‍​⁠‍‍​‍​‍‌‍⁠‍‌‍‌‌‌⁠‌⁠‌‌⁠⁠‌⁠‌​‌‍⁠⁠‌⁠​​‌‍‍‌‌‍​⁠​‍​‍​‍⁠​​‍​‍‌‍‍‌‌‍‌​​‍​‍​⁠‍‍​‍​‍‌‍⁠‍‌‍‌‌‌⁠‌⁠​‍​‍​‍⁠​​‍​‍‌‍‌​​‍​‍​⁠‍‍​‍​‍​⁠​‍​⁠​​​⁠​‍​⁠‌‌​⁠​‌​⁠​‍​⁠​‌​⁠‍​​‍​‍​‍⁠​​‍​‍‌‍‍​​‍​‍​⁠‍‍​‍​‍‌‍‍‍‌​‍‍‌⁠​‌​⁠‍​‌⁠​​‌‍⁠⁠‌​‍‍‌‍‍​‌‍⁠⁠‌‍‍⁠‌‍‌​​⁠‌‌‌​‍‌‌‌​‍‌‌‌⁠‌‌​​​‍​‍‌⁠⁠‌​

@OP we started pre-marking the back and ribs with a 1.5 m paint grid before the round, which cut our bolt install time enough to stay inside the “30‑minute unsupported window” in 3.5 m headings using 2.4 m resin. Small caveat: in wet “rainfall” conditions the 50 mm early‑strength shotcrete would wash/rebound at the brow, so we bump accelerator or go 60–70 mm with fibers there.

‌⁠‍⁠​‍​‍‌⁠‌​​‍​‍​⁠‍‍​‍​‍‌‍‌⁠‌‍⁠‌‌‍‍‍​⁠​‍​‍​‍​‍⁠​​‍​‍‌‍‍⁠​‍​‍​⁠‍‍​‍​‍‌⁠​‍‌‍‌‌‌⁠​​‌‍⁠​‌⁠‍‌​‍​‍​‍⁠​​‍​‍‌‍‍‌‌‍‌​​‍​‍​⁠‍‍​⁠​‍​⁠​⁠​⁠‍​​⁠‌⁠​⁠​⁠​‍⁠​​‍​‍‌‍‌​​‍​‍​⁠‍‍​‍​‍​⁠​‍​⁠​​​⁠​‍​⁠‌‌​⁠​‌​⁠​‍​⁠​‍​⁠​⁠​‍​‍​‍⁠​​‍​‍‌‍‍​​‍​‍​⁠‍‍​‍​‍​‍⁠‌‌‍‌‌​⁠‌​‌​‍⁠‌​⁠⁠‌‍‍‌‌​‍​‌​⁠​‌⁠‍‍‌⁠​⁠‌‍​‌‌‍‍​‌‍‍​‌‍​‍‌​‍⁠‌⁠​‌​‍​‍‌⁠⁠‌​​